RioZim Limited’s third quarter of 2026 marked a significant turnaround in gold production, with the company producing 177 kg of gold, a stark contrast to the near-zero production in the same period last year. The recovery was driven by the stabilisation of production at Cam & Motor mine and consistent output from Renco mine, despite challenges posed by ageing infrastructure.
Output, however, was constrained by ageing infrastructure. The Group produced 177 kg of gold for the third quarter and 389 kg for the nine months to September 2026, representing a marked turnaround from the comparative period in the previous year during which the Group’s mines were shut down and production was almost nil.
Cam & Motor mine, which resumed production in the first half of the year, contributed 70 kg of gold in the quarter, bringing its nine-month total to 98 kg. Renco mine produced 107 kg, with cumulative production reaching 291 kg for the nine months. However, the mine’s operations remain constrained by limited reserves and ageing equipment, necessitating substantial investment to sustain future production.
The favourable gold price, above US$4,000/oz, supported revenue growth. Looking ahead, RioZim has a clear roadmap for growth. Through an Extraordinary General Meeting held on 21 October 2026, the Company obtained unanimous shareholders’ approval for the disposal of Renco mine to raise funding to deleverage and strengthen the Company’s balance sheet. The Company will also channel a portion of the proceeds towards stabilising Cam & Motor mine and bringing production to an optimal level following the mine’s resumption of operations earlier in the year.
At Cam & Motor mine, the installation of the second mill has progressed significantly and testing has commenced with full commissioning scheduled for completion before year-end. The second mill will increase milling throughput and provide an alternative in the event of a breakdown of the first. Construction of a new Tailings Facility at the mine which commenced earlier in the year is progressing well and remains within targeted timelines with commissioning scheduled for the first half of the ensuing year.
Meanwhile, Dalny mine continued small-scale operations, supporting the Chakari community, while Empress Nickel Refinery remained under care and maintenance. The company also disposed of its interest in RZM Murowa (Private) Limited in the second quarter.